Institutional
DTM Development, Ltd. and David Niemotko Architects, P.C. was
selected as the lowest priced, most qualified bidder for this
design/build project which consisted of the construction of a new, 1
½ story, 10,000 square foot, brick building with substantial
development to the 1 ½ acre site. The garage is designed to
accommodate six ambulances, explosion resistant storage, offices, a
mezzanine and a de-contamination room. Many of the garage rooms are
constructed with fire rated partitions / ceilings and the concrete
slab is epoxy coated. The remaining portions of the building are
designed to include a multi-purpose room, kitchen, offices,
mechanical room, bathrooms, an egress stair enclosure and a vertical
conveyor. The mechanical systems for the garage include a radiant
floor heating system and a make-up” air system, while the remaining
portions of the building have a forced air system for heating and
cooling. The entire building, including the attic, is protected with
a sprinkler system. Site development included underground trenching
and “street opening” procedures for the gas, electric and water
services to the building, a parking lot area, detention basin, site
lighting, fencing and landscaping. Regulatory permitting involved
the Building Department and Department of Public Works, with bank
inspections and local utility company coordination. DTM Development
was able to adhere to the client’s time constraints and budget
stipulations for this project.
Services provided:
Architecture
Engineering
Value engineering/ Cost analysis
General Contracting/ Construction Management
VA MEDICAL CENTER, CASTLE POINT, NEW YORK – PHASE 1
David Niemotko was selected as the project manager for the first
phase of this construction project, which included two, 20,000
square feet (in total), Nursing Home Care Unit buildings. These
two-story, steel frame buildings consist of new patient rooms, ADA
compliant bathrooms, and medical stations, which connect to existing
buildings. The exterior walls were constructed with brick and
concrete block, with aluminum framed windows and pre-cast concrete
sills. The metal stud roof system has rigid insulation and roof
shingles. The concrete foundation system involved “deep” excavation
to align with the existing building’s foundation. The mechanical
systems include forced air for heating and cooling, sprinklers and
plumbing to each of the rooms.
Services Provided:
General Contracting
VA MEDICAL CENTER, CASTLE POINT, NEW YORK – PHASE 2
David Niemotko was selected as the project manager for the second
phase of this project, which included a new “Multi-Purpose” building
and exterior “corridors” connecting the two phases. The new brick
and concrete block “Multi-Purpose” building has a steel frame
structure, while the exterior “corridor” buildings are constructed
utilizing metal stud exterior walls with clapboard siding, and metal
stud frame roof with shingles.
Services Provided:
General Contracting
Both projects were completed on time in accordance with the contract
schedule.